Minotaur NFIRE Launch - april 24 Updates |
![]() ![]() |
Minotaur NFIRE Launch - april 24 Updates |
Aug 20 2008, 08:33 PM
Post
#1
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-23 at 20:53:28 EST
At 8:48 p.m. The countdown is at the T-6 hour point for the launch of the Air Force Minotaur 1 rocket carrying the Missile Defense Agency's Near Field Infrared Experiment (NFIRE) satellite. The launch window for this attempt is 2:48 to 3:03 a.m., Tuesday, April 24. During the past hour and the next one, the Wallops range will be checking out radar, telemetry and other support systems. Initial set-up of the rocket begins at T-5 hours. |
|
|
|
| Googlebot |
Aug 20 2008, 08:33 PM
Post
#
|
|
![]() |
|
|
|
|
||
Aug 20 2008, 08:33 PM
Post
#2
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-23 at 21:48:49 EST
At 9:48 p.m. T-5 hours and counting. The Wallops range has completed its initial checks of its support systems for the launch. During the next hour the rocket team will conduct its initial set-up of the launch vehicle and range set-up. The weather at Wallops is 61 degrees, clear skies and winds around 17 mph out of the SSW. |
|
|
|
Aug 20 2008, 08:33 PM
Post
#3
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Monday, April 23 2007 @ 10:26 PM MST
Re:Minotaur NFIRE Launch - april 24 Updates Posted by RCC on 2007-04-23 at 22:48:00 EST 10:48 p.m. T-4 hours and counting. The vehicle and range set up are complete. The weather forecast for launch: 58 degrees, winds at 15 knots from the SSW, broken /layered mid-level clouds. Only a 15% chance of weather violation for launch. Countdown is running smoothly to this point. At the launch pad the gantry is being removed from around the Minotaur. The launch team is continuing with vehicle test. |
|
|
|
Aug 20 2008, 08:33 PM
Post
#4
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-23 at 23:48:32 EST
11:48 a.m. T-3 hours and counting. Launch vehicle checkout is complete. During the next hour the launch team will begin final vehicle arming and closeout. |
|
|
|
Aug 20 2008, 08:33 PM
Post
#5
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 00:48:18 EST
12:48 a.m. T-2 hours and counting. Weather remains favorable for launch. Launch team is continuing final arming and vehicle closeout. |
|
|
|
Aug 20 2008, 08:34 PM
Post
#6
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 01:48:00 EST
1:48 a.m. T-60 minutes and counting. Arming and vehicle closeout is complete. Telemetry and radar systems have been calibrated. Range is ready to proceed. The initiation of the final launch checklist has started. |
|
|
|
Aug 20 2008, 08:34 PM
Post
#7
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 01:58:00 EST
T-50 minutes and counting. Telemetry link checks have been completed. Weather is go for launch. |
|
|
|
Aug 20 2008, 08:34 PM
Post
#8
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 02:08:05 EST
2:08 a.m. T-40 minutes and counting. |
|
|
|
Aug 20 2008, 08:34 PM
Post
#9
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 02:18:06 EST
2:18 a.m. T-30 minutes and counting. |
|
|
|
Aug 20 2008, 08:34 PM
Post
#10
|
|
|
Administrator ![]() ![]() ![]() Group: Root Admin Posts: 781 Joined: 10-August 08 Member No.: 1 |
Posted by RCC on 2007-04-24 at 02:27:54 EST
2:28 a.m. T-20 minutes and counting |
|
|
|
![]() ![]() |